Analisis Manajemen Waktu Dan Biaya Menggunakan Metode Critical Path Method (CPM) Pada Proyek Gedung Rumah Hunian

(Studi Kasus Pembangunan Rumah 2 Lantai)

Authors

  • Wilson Pabidang Universitas Pendidikan Muhammadiyah Sorong
  • Athiah Safari Universitas Pendidikan Muhammadiyah Sorong
  • Elfiyusriningsi Syara Universitas Pendidikan Muhammadiyah Sorong

Keywords:

Manajemen Waktu, CPM, Lintasan Kritis, Biaya

Abstract

Time management is an essential factor in the success of construction projects, as delays often lead to financial losses and reduced quality of work. Therefore, an appropriate method is needed for effective planning and control. One method that can be applied is the Critical Path Method (CPM), which is able to identify the critical path, project duration, and activities that must not be delayed. This study aims to analyze project time efficiency using CPM and to calculate direct costs based on the work volume derived from construction drawings using the Analisis Harga Satuan Pekerjaan (AHSP). The data used include the project schedule, activity durations, task dependencies, and work volumes. The analysis results show that the total project duration is 178 days, with the critical path consisting of mobilization, bowplank installation, earthwork, foundation, lean concrete, main structure, roofing, finishing, and final cleaning. All critical activities have no available float, meaning that any delay in one activity will affect the overall project duration. The direct project cost calculated using AHSP is Rp 1,478,634,218. Thus, the application of CPM proves useful in identifying critical activities, optimizing project scheduling, and providing a basis for decision-making to minimize delays in project implementation.

References

Afiya, S. N., & Alhaq, A. S. (2023). Analisis penerapan manajemen waktu dengan metode CPM pada proyek pembangunan perumahan griya mahari Analysis of implementation time management using CPM method in griya mahari housing development project. Jurnal Terapan Teknik Industri, 4(November), 271–283.

Hansastri, H., & Hamdani, H. (2024). Sinkronisasi dan Sinergitas Proyek Infrastruktur Prioritas dan Proyek Strategis Nasional dengan Perencanaan Nasional dan Daerah. Menara Ilmu, 18(2), 26–36.

Pramesti, H. R. (2023). Analisa Pengendalian Waktu Dengan Metode Critical Path Method (Cpm) Pada Proyek Pembangunan Pondok Iqro’, Surakarta. Prosiding Seminar Nasional Teknik Sipil, 1(1), 560–566.

Sebayang, S. M., & Sondakh, E. (2023). Penerapan Metode Cpm Dalam Penjadwalan Produksi Di Pt Xyz Divisi. Jurnal Logistik Bisnis, 13(2), 8–15.

Sinurat, F., & Misdalena, F. (2024). Analisis Manajemen Proyek Dengan Metode Critical Path Method ( CPM ) Pada Proyek Pembangunan Gedung Chandra Tanjung Karang. 2–11.

Safitri, R. A., Makrifa, A. I., & Apriliana, Y. (2023). Analisa Optimalisasi Waktu Terhadap Time Schedule Dengan Menggunakan Cpm (Critical Path Method) Pada Masa Pandemi Covid-19. Structure, 4(1), 32.

Saputra, N., Handayani, E., & Dwiretnani, A. (2021). Analisa Penjadwalan Proyek dengan Metode Critical Path Method (CPM) Studi Kasus Pembangunan Gedung Rawat Inap RSUD Abdul Manap Kota Jambi. Jurnal Talenta Sipil, 4(1), 44.

Sebayang, S. M., & Sondakh, E. (2023). Penerapan Metode Cpm Dalam Penjadwalan Produksi Di Pt Xyz Divisi. Jurnal Logistik Bisnis, 13(2), 8–15.

Tjendani, H. T., & Ramadhan, K. (2022). Critical Path Method Pada Proyek Myze Hotel Sumenep Untuk Mengendalikan Biaya Dan Waktu. Jurnal Kacapuri : Jurnal Keilmuan Teknik Sipil, 5(1), 240.

Wasito, & Syaikhudin, A. Y. (2020). Studi Penerapan Critical Path Metode (cpm) Pada Proyek Pembangunan Pabrik Semen Rembang Pt Semen Gresik. 2507(February), 1–9.

Widodo, W., & Hermansyah, B. (2023). Analisis Keterlambatan Pelayanan Komplain Nasabah Bank Menggunakan Metode Critical Path Method. Jurnal Informatika Komputer, Bisnis dan Manajemen, 20(2), 23–33.

Published

2025-09-30

How to Cite

Pabidang, W., Safari, A., & Syara, E. (2025). Analisis Manajemen Waktu Dan Biaya Menggunakan Metode Critical Path Method (CPM) Pada Proyek Gedung Rumah Hunian : (Studi Kasus Pembangunan Rumah 2 Lantai). BINER : Jurnal Ilmu Komputer, Teknik Dan Multimedia, 3(3), 325–338. Retrieved from https://journal.mediapublikasi.id/index.php/Biner/article/view/5689